LAX Terminal 7 & 8 Baggage Handling System
Miscellaneous Metals • Equipment Installation
Los Angeles, CA
Mechanical installation of a new Checked Baggage Inspection System (CBIS) serving Terminals 7 and 8 at LAX, including conveyor systems, support steel, access platforms, guarding, and system readiness for integrated testing and commissioning.
Mechanically installed the complete CBIS Part B baggage handling system, including conveyors, belt curves, merges, sorters, queue conveyors, and associated mechanical components.
Furnished and installed header steel, seismic bracing, sway bracing, catwalks, handrails, ladders, impact protection, stanchions, and sheet metal under-guarding required to support and protect the conveyor system.
Performed belt cutting, lacing, tensioning, tracking, mechanical run testing, static checks, and supported load testing and commissioning activities leading up to system acceptance.